Interactive map of the best practices

on the use of water, land and energy resources,
as well as the environment of Central Asia

Comparison of practices

Название практики Land reclamation via vertical drainage wells Improving reclamation condition of arable land around West Karmakshi Collector
Category Water resources Water resources
Tool Collector-drainage system Collector-drainage system
Field of application

• Use of water resources
• Use of land resources

• Use of water resources
• Use of land resources

Usability of practice for adaptation to climate change Moderate Moderate
Implemented by Ministry of Reclamation and Water Management of the Republic of Kazakhstan

Used by

Country: Kazakhstan

Province: South Kazakhstan Region

District: Maktaaral District

Country: Kazakhstan

Province: Kyzylorda Region

District: Karmakshy District

Other settlement: a/o “Aktobe”, a/o “III International”

Local specifics

• Upstream (Ferghana) and midstream (Syr Darya) of the Syr Darya River
• Ebb occurrence of highly mineralized ground water

The site is located in the lower reaches of the Syr Darya River (inter-riverbed depression strip)

Practice usage period

Start date: 01.01.1965

End date: 31.12.1975

Start date: 01.01.2010

End date: 31.12.2011

Problem solved through this practice

Deterioration of reclamation situation: rising of ground water, land salination

Increasing secondary land salination, deterioration of col-lector and drainage system (CDS)

Tools used in the practice

Technique and technology of land reclamation via a system of vertical drainage wells (VDW)

A set of measures to enhance land reclamation condition (collector cleaning using special equipment, reconstruction of hydraulic engineering installations, etc.)

Description of the practice and its results

Actions:

A VDW system set up. Prior to its installation, the area was drained via a horizontal open-type drain-age network ineffective as to reducing the mass of salinized land.

Comprehensive VDW efforts significantly enhanced drainage.


However, currently due to the absence of a single organization responsible for VDW operation, maintenance and repair, the VDW systems recon-structed under World Bank and Asian Development Bank projects do not perform as effectively as ini-tially.

Results:

Financial and economic:
Increased cotton yields (from 10-15 up to 30-35 dt/ha).

Technical:
Successful response to land salination in 3 districts: ground water table steadily kept at 2-3 m depth leading to a sharp contraction of salinized land area.

Actions:
The capital repair of inter-farm West Karmakshi Collector (WKC) is necessitated by the fact that in its current condition the Collector didn't provide for timely drainage of drainages and discharge water from cropland in the Left-Bank Massif.

Results:

Financial and economic:
Increased crop productivity, mainly rice and forage crops

Technical:
Enhanced reclamation condition of land in the Left-Bank Massif

Lessons learnt and recommendations made

Lessons learnt:

In due time, the model proved useful and timely, as the country urgently needed to increase its cotton yields. The practice demonstrated high efficiency of VDW in combatting land salination.

Recommendations:

1. Establish a special VDW System Maintenance and Operation Department;
2. Build personnel capacity:
• Continual training of personnel in the Department and Provincial Hydrogeological and Land Reclamation Expedition;
• Drafting and distribution of training materi-als.

Lessons learnt:
Allocation of resources for cleaning CDS proved more efficient than other target actions

Recommendations:
Regular and timely execution of running and capital collector cleaning is necessary to ensure its proper operation

Source of practice

Domestic tools (outcomes of research by domestic R&D organizations)

Domestic tools (outcomes of research by domestic R&D organizations)

Readiness for implementation

1. Cost of implementation: Moderate

2. Approximate cost of investment per 1 ha:

3. O&M costs: High

4. Expert support: Not needed

1. Cost of implementation: High

2. Approximate cost of investment per 1 ha:

3. O&M costs: High

4. Expert support: Not needed

Brief information on the project
Funding source Ministry of Reclamation and Water Management of the USSR Ministry of Reclamation and Water Management of the Republic of Kazakhstan
Information sources

Reshetkina N.M. et al. “Vertical Drainage”, Moscow: Kolos, 1978. – 319 p.

Contacts of a person, who filled this form

SIC ICWC

SIC ICWC

Form submission date 26.03.2018 29.03.2018

Partners