Interactive map of the best practices

on the use of water, land and energy resources,
as well as the environment of Central Asia

Comparison of practices

Название практики Set of hydro-reclamation measures Повышение водообеспеченности пастбищ путем строительства сардоб
Category Water resources Water resources
Tool Set of hydro-reclamation measures System for enhancing water availability
Field of application
  • Use of water resources
  • Use of land resources
  • Environmental protection
  • Использование водных ресурсов
  • Использование земельных ресурсов
  • Охрана окружающей среды
Usability of practice for adaptation to climate change Low Moderate
Implemented by Ministry of Nature Protection of Turkmenistan and German Technical Cooperation Agency (GIZ)
Министерство охраны природы Туркменистана
Used by

Country: Turkmenistan

Province: Mary Region

District: Sakarçäge District

Other settlement: Zakhmet Daikhan Farm

Country: Turkmenistan

Province: Ahal Region

District: Derweze District

Local specifics

Sakar-Chaga District (area of 53,000 ha; population of 132,000 people) is located in the northwestern part of Mary Region in the Murgab River delta. The majority of local residents live in the oasis hosting 80% of settlements.

17238 га барханных, такырных и солончаковых участков пустыни Каракум;
Глубокое залегание грунтовых вод.

Practice usage period

Start date: 01.01.2009

End date: 31.12.2010

Start date: 01.01.2012

End date: 31.12.2016

Problem solved through this practice

Land salination represents the main challenge in the area due to improper irrigation technology and lack of drainage, in their turn leading to extremely low productivity. With time, the existing irrigation management system resulted in irrational use of water and land. While water distribution rates were calculated in a centralized manner depending on specific crops, in practice water supply monitoring is extremely poor – water supply (canals) infrastructure is inconsistent with farmers’ needs leading to excessive and, vice versa, insufficient watering of different sites. In addition, there exists an informal water payment system leading to the advantageous position of certain users.

Опустынивание земель и снижение продуктивности пустынных пастбищ в результате перевыпаса вокруг существующих водопоев скота

Tools used in the practice

Set of hydro-reclamation measures: preventive land forming (leveling), composting, monitoring of ground water bedding and mineralization, decentralized water management planning, capacity building, etc.

Технология строительства сардоб для повышения водообеспеченности пастбищ

Description of the practice and its results

Actions:

A series of measures were executed to prevent land degradation and improve land reclamation condition, including introduction of high-performance drainage systems and reclamation technologies, construction of a new collector and cleaning of the existing one, construction of 9 water-regulating and 2 water-measuring facilities.

Results:

  • 50 hectares of degraded land rehabilitated and can be used for agricultural purposes. About 35 ha of land saved from degradation thanks to preventive land forming;
  • regular seminars held for land users on potential ways of applying various advanced methods of maintaining rural economy and effective use of water resources;
  • about 60 measuring stations installed to monitor the level and mineralization of ground water.

Основные мероприятия:

  • Оценка рисков селей и паводков и выявление пожеланий местного населения в отношении размещения.

Мероприятия:

• Выбор такыров для устройства сардоб совместно с местными скотоводами;
• Строительство сардоб с участием местных скотоводов; 
• Очистка поверхности такыра.

Результаты:

• Участки пастбищ, ранее не использовавшиеся из-за отсутствия источников воды, возвращены в пастбищеоборот; 
• Началось восстановление пастбищ, пострадавших от перевыпаса; 
• Повысились продуктивность стада из-за сокращения дистанций перехода и увеличения кормовой ценности пастбищ.

Lessons learnt and recommendations made

Lessons learnt:

  • salinized land was rehabilitated not only thanks to reclamation actions but also by composting. In particular, high-quality humus is produced to enhance soil salinity parameters;
  • the process of designing water use plans for individual farmers launched;
  • one new collector built.

Recommendations:

It is necessary to focus on strengthening the role of local associations in rendering irrigation services and managing the canal’s water level.  Local water users will be rendered an opportunity to design effective irrigation water management schemes.  The experience of decentralized water planning and management accumulated by water tenants will be documented and distributed as a part of knowledge-management (capacity-building) strategy.  It is necessary to closely cooperate with the newly established Agriculture Advisory Service working on sustainable land and water management, as well as to disseminate corresponding practices in other areas.

Уроки:

Строительство сардоб на такырах позволяет повысить водообеспеченность пастбищ, что способствует восстановлению пастбищ, пострадавших от перевыпаса скота».

Рекомендации:

Эта практика требует долгосрочного планирования и комплексных подхода с вовлечением на начальной стадии специалистов по борьбе с опустыниванием (определение комплекса мер по защите такыра от песчаных заносов), государственных структур (техническая помощь) и пользователей пастбищ (соблюдение оборота пастбищ, охрана такыров от засорения и загрязнения).

Source of practice

Domestic tools (outcomes of research by domestic R&D organizations)

Традиционные инструменты, передаваемые из поколения в поколение и показавшие ценность в современных условиях

Readiness for implementation

1. Cost of implementation: High

2. Approximate cost of investment per 1 ha:

3. O&M costs: High

4. Expert support: Not needed

1. Cost of implementation: Low

2. Approximate cost of investment per 1 ha: От 1000 до 5000 USD

3. O&M costs: Low

4. Expert support: Needed at implementation stage

Brief information on the project

Project title: Local-level capacity building and investment for sustainable management of land resources.

Project duration: 2009-2010.

Project goal and objectives: overcoming barriers to higher efficiency and performance of water supply systems in climate change induced drought conditions.

Project beneficiaries: Zakhmet Daikhan Farm (approximately 300 daikhan households).

Project implementer: Ministry of Nature Protection of Turkmenistan and German Technical Cooperation Agency (GIZ).

Название: Реагирование на риски, связанные с изменением климата, на систему дайханского хозяйства в Туркменистане на национальном и местном уровнях.

Продолжительность: 2012-2016 гг.

Цели и задачи: Усилить адаптационный потенциал для реагирования на воздействия по причине изменения климата, включая изменчивость на местном и национальном уровнях.

Получатели выгод от реализации проекта: Посёлок «Бори» с численностью населения более 1100 человек и посёлок «Бокурдак» с численностью населения около 4500 человек.

Структура, ответственная за реализацию проекта: Министерство охраны природы и ПРООН.

Донор: Адаптационный Фонд

Funding source UNDP and Global Environmental Facility Правительство Туркменистана, Адаптационный Фонд
Information sources

http://www.turkmenistan.ru/?page_id=3&lang_id=ru&elem_id=17207&type=event&layout=print&sort=date_desc 

tm.undp.org

Contacts of a person, who filled this form

SIC ICWC

НИЦ МКВК

Form submission date 17.04.2018 22.08.2017

Partners