Название практики | Restoration of irrigation infrastructure in mountainous regions of Kyrgyzstan | Мелиорация земель системой скважин вертикального дренажа |
---|---|---|
Category | Water resources | Water resources |
Tool | Restoration of water management infrastructure | Collector-drainage system |
Field of application |
|
|
Usability of practice for adaptation to climate change | Moderate | Moderate |
Implemented by | Mountain Societies Development Support Programme Kyrgyzstan (MSDSP KG) on the initiative of Aga Khan Foundation |
Министерство мелиорации и водного хозяйства Казахской ССР |
Used by |
Country: Kyrgyzstan Province: Osh Region District: Nookat District |
Country: Kazakhstan Province: South Kazakhstan Region District: Maktaaral District |
Local specifics | The northeastern part of Osh Region lies in the Tien Shan spurs (Fergana Range) with the Pamir-Altai Mountains in the south and west (Turkestan, Alai, Trans-Alai (Lenin Peak) Ridges. The climate in the region is sharp continental. The Kyzyl-Suu, Ak-Buura and Kara Darya are the largest rivers in the area used for irrigation. |
|
Practice usage period |
Start date: 01.01.2013 End date: 31.12.2016 |
Start date: 01.01.1965 End date: 31.12.1975 |
Problem solved through this practice | Conflicts due to disputes over water resources and pastures |
Ухудшение мелиоративной обстановки: подъем грунтовых вод, засоление земель. |
Tools used in the practice | Repair works to restore irrigation networks and infrastructure |
Техника и технология мелиорации земель системой скважин вертикального дренажа (СВД) |
Description of the practice and its results | Disputes over water resources and pastures can lead to conflicts, in particular among the communities living in border zones in the Fergana Valley. Every year, this urgent issue gains even more relevance as - according to expert forecasts – by 2020 Kyrgyzstan’s population may reach 7 mln 70% of which will live in rural communities. Actions: The project to rehabilitate irrigation canals aimed to improve access to water resources and pastures for local residents. The project also promoted introduction of equal-right practices in the sphere of water resources and pastures management among local population. All project actions targeted the improvement of living conditions of local residents and decreasing tensions. Results: On June 8, 2016, Aga Khan Foundation (AKF) and Aga Khan Development Network (AKDN) held the ceremonial opening of 5 repaired irrigation canals in Nookat District of Osh Region. Repair works to rehabilitate the irrigation canals were co-funded by Nookat District Water Management Administration, ajyl aimaks (Kyrg. rural local governance bodies) and local residents themselves. Financial and economic:
Environmental: The condition of over 4,000 ha (irrigated land) improved. Technical results: The total length of all repaired irrigation canals exceeded 10,900 meters. Social results:
|
Мероприятия: Внедрена СВД. До внедрения СВД рассматриваемая территория дренировалась горизонтальным дренажем открытого типа, что не обеспечивало сокращение площади засоленных земель. Результаты: Финансово-экономические: Технические: |
Lessons learnt and recommendations made | Lessons learnt: Repair and restoration of irrigation infrastructure facilitated the improvement of living conditions among local population, decreased tensions and disputes associated with water and pasture use in border zones of the Fergana Valley, and enhanced farmer welfare. Recommendations: The practice yielded positive outcomes and is recommended for further scaling-up to improve the welfare and ensure sustainable development of mountain communities in border zones. |
Уроки: Этот пример был в свое время очень полезным и своевременным, так как стране очень требовалось повысить урожайность хлопчатника. Практика показала высокую эффективность применения СВД в борьбе с засолением земель. Рекомендации: 1. Создание специального Управления по ремонту и эксплуатации систем СВД.
|
Source of practice | Foreign tools (transfer of foreign experience) |
Отечественные инструменты (результат разработок отечественных научно-исследовательских структур) |
Readiness for implementation |
1. Cost of implementation: High 2. Approximate cost of investment per 1 ha: 3. O&M costs: High 4. Expert support: Not needed |
1. Cost of implementation: High 2. Approximate cost of investment per 1 ha: 3. O&M costs: Moderate 4. Expert support: Needed at O&M stage |
Brief information on the project | Project title: Improving infrastructure and building capacity of relevant local institutes on effective management of water and pasture resources. Project duration: 2013-2016. Project goal and objectives: enhance welfare and ensure sustainable development of mountain communities, prevent conflicts, facilitate stability and security of using natural resources in border zones. Scale of implementation and project beneficiaries: populations of Nookat and Aravan Districts, town of Kyzyl-Kiya. Project implementer: Mountain Societies Development Support Programme Kyrgyzstan (MSDSP KG). |
|
Funding source | Aga Khan Foundation and the UK Embassy in Kyrgyzstan | Министерство мелиорации и водного хозяйства СССР |
Information sources | Mountain Partnership Member News (www.ekois.net) |
Решеткина Н.М. и др. «Вертикальный дренаж», Москва: Колос, 1978. – 319 с. |
Contacts of a person, who filled this form | SIC ICWC |