Название практики Introduction of Integrated Water Resources Management (IWRM) principles on the Aspara small transboundary river Water-charging irrigation for rangelands used for growing forage crops
Category Water resources Water resources
Tool Public participation principle Irrigation technique and technology
Field of application

Use of water resources

• Use of water resources
• Use of land resources

Usability of practice for adaptation to climate change High High
Implemented by USAID/CAREC

Used by

Country: Kyrgyzstan

Country: Kazakhstan

Province: Jambyl Region

District: Talas District

Other settlement: Village of Sadu Shakirov

Local specifics

Transboundary river

The site is located in the desert foothill plain in South-ern Kazakhstan (internal drain area) at the very end of Sharuashlyk Irrigation Canal.

Practice usage period

Start date: 01.04.2012

End date: 31.10.2016

Start date: 01.05.2008

End date: 30.04.2009

Problem solved through this practice

Imperfections of the water management mechanism in the Isfara small transboundary river basin

Acute water shortage; land degradation in the village of Sadu Shakirov; abandoned irrigated arable lands used only for year-round cattle grazing.

For a long time, the irrigation canal was not operation-al and, thus, became dilapidated. The situation in the area was aggravated by climate change impacts (de-creased quantity of early spring, summer and winter precipitation, increased average annual temperature, spring and autumn frost bites and summer droughts).

Tools used in the practice

The principle of stakeholder engagement in decision-making associated with water management of small transboundary river; IWRM planning technique

Method of autumn and winter water-charging irrigation

Description of the practice and its results

The Aspara River originates in the Western Tien Shan on the territory of Kyrgyzstan and flows northwards crossing the border with Kazakhstan.  The river’s total length exceeds 44 km, and its catchment area amounts to approximately 66 km2.  The Aspara River Basin is located in Chu Region in Kyrgyzstan’s northwest and Jambyl Region in Southern Kazakhstan.  The basin is shared by several different ethnicities where they live and work.  The basin’s population is rapidly growing, and the agriculture is developing.  In many places along the course of the river, especially in its lower streams, the water doesn't meet quality and sanitary standards.  Liquid waste produced by the population, industry and livestock production as well as solid waste constitute major sources of environmental pollution.

Project efforts were carried out in Jambyl Region of the Republic of Kazakhstan and Chu Region of the Kyrgyz Republic.

Actions:

Establishment of 2 stakeholder groups, i.e. Small Basin Councils (SBC) – on both Kazakhstan’s and Kyrgyzstan’s sides of the river – representing local authorities, NGOs, water users and local communities.  The SBCs already held 6 joint meetings proving the value of SBCs as platforms to exchange opinions and information as well as take joint decisions on enhancing the overall situation in the basin.

In addition, hydrometric posts were reconstructed and underwent certification, and the automated water distribution and accounting system was installed on the Mailybai Canal. The water supply system in the village of Cholok-Aryk also underwent reconstructed.  A demo-site to demonstrate drip irrigation equipment and technology was established on the premises of Ravshan Farm receiving its irrigation water via the Mailybai Canal.

Results:

Thus, the creation of national Small Basin Councils (SBC) on the Aspara River ensured a platform for exchanging opinions and information as well as joint decision-making to improve the overall situation in the Aspara River Basin, including the development of the IWRM basin-specific plan.

Actions:
1) Reconstruction of the canal, stop-gates and field irrigation networks (rehabilitation of irrigation furrows),
2) Setting up artificial pastures with forage crops

Results:

Financial and economic:
Using water-charging irrigation for rangelands allowed increasing their productivity from 3.5 to 5 dt/ha and receiving 60 tons of herbage for cattle and sheep and goats from non-cultivated land.

Technical:
1) 12 km of the canal and 5 stop-gates to regulate water releases restored,
2) 5 km of irrigation furrows built,
3) Cultivated pastures with forage crops created (soil preparation, alfaalfa planting, coordination of irrigation norms),
4) Fields are prepared during the summer-fall period, and watered during late fall or early spring.

Lessons learnt and recommendations made

Lessons learnt:

Introduction of IWRM principles is the pre-requisite of stable and fair water supply irrespective of a given water user’s location.

Recommendations:

Currently, when local stakeholders are represented in SBCs and are engaged in joint water management, it is necessary to continue the capacity-building efforts to build-up SBCs’ efficiency.  In the long term, it might be necessary and possible to establish a joint body to manage the whole Aspara River Basin shared by Kazakhstan and Kyrgyzstan.

Lessons learnt:
Application of water-charging irrigation allowed in-creasing water availability and, as the result, productivity of agricultural crops.

Application of water-charging irrigation demonstrated the efficiency of water use and allowed local popula-tion to go through winter without losing livestock.

Recommendations:
The method can be used in areas/communities where along with crop growing the population is also involved in livestock breeding.

Source of practice

Foreign tools (transfer of foreign experience)

Traditional tools transferred from generation to generation that proved their efficiency in modern conditions

Readiness for implementation

1. Cost of implementation: High

2. Approximate cost of investment per 1 ha:

3. O&M costs: High

4. Expert support: Not needed

1. Cost of implementation: High

2. Approximate cost of investment per 1 ha:

3. O&M costs: High

4. Expert support: Not needed

Brief information on the project

Development and implementation of basin plans constitute principal elements of integrated water resources management.  Multi-agency coordination mechanism via basin councils or coordination groups is an important advantage of IWRM.  This approach allows streamlined coordination and synergy of actions on all levels of management hierarchy.

Project title: Stakeholder partnership in joint policy-making: assistance to transboundary cooperation in small watersheds of Central Asia.

Project duration: Apr 2012-Oct 2016

Project goal and objectives: introduction of the integrated water resources management (IWRM) practice in three transboundary watersheds and its scaling-up in Central Asia.

Project beneficiaries: communities of the Aspara small transboundary river basin, specialists of water and environmental agencies, farmers.

Project implementer: USAID/CAREC.

Project title: Fall and early spring Irrigation of arable land and pastures as an adaptation mechanism of ra-tional water use in Southern Kazakhstan

Duration: May 1, 2008 – April 30, 2009

Project goal and objectives: reduce land degradation due to climate change by way of rational use of irriga-tion water. The project was implemented to prevent loss of cattle due to forage shortage during alternating droughty years.

Project beneficiaries: local population.

Project implementer: Kogal LLC

Funding source USAID Kogal LLC
Information sources

carecnet.org

1) UNDP Compilation “Climate change adaptation: ex-amples from Uzbekistan and Kazakhstan”, Tashkent 2012;
2) pandia.org

Contacts of a person, who filled this form

SIC ICWC

SIC ICWC

Form submission date 02.04.2018 29.03.2018